81001ISO 81001-1 Revision Checker
The revision record Retrieved 21 October 2026 Stage 40.20 ยท DIS ballot initiated: 12 weeks Planning date 14 Sep 2027, an estimate
The dated plan

A dated plan from the ballot to the published second edition

The dates ISO records, the dates this site derives from them, and the ones that are only an estimate. Each line carries its status so a plan can be built without borrowing certainty the record does not have.

THE LADDER

Where the document is, and what comes next

The official page
  1. 40.20DIS ballot initiated5 October 2026, recorded

    The draft is with national bodies for a 12 week enquiry. Comments and votes are being collected.

  2. 40.60Close of votingNot recorded. A 12 week ballot from 5 October would close on 28 December 2026.

    The ISO page does not record this date. The arithmetic is shown so a plan can use it, labelled derived.

  3. 50.00ApprovalNot recorded

    The final text is received or an FDIS is registered. The timing depends on the vote and the comments.

  4. 60.60Published14 September 2027, an estimate

    The planning date used on this site. It is not an ISO commitment and it will move if the ballot does.

How the estimate was made

An estimate for planning, 330 days from the build date of 19 October 2026 and 344 days from the recorded 40.20 date of 5 October 2026. ISO has not recorded a 40.60 date, a 50.00 date, a 60.00 date or a 60.60 date. The date is labelled an estimate wherever it appears and is not an ISO commitment.

What would change it

A recorded 40.60 date, a comment resolution that needs a second ballot, an FDIS stage, or a publication date. Each one is a change the watch sends. The estimate is replaced, not defended.

Your national member body

The ballot is with ISO's national members. Comments and votes go through the member body for your country, not through this site. A 12 week ballot from 5 October would close on 28 December 2026; ask your member body for its own comment deadline and, after the vote, for the ballot report. The committee is ISO/TC 215, Health informatics.

What to put in your plan

Work back from the estimate: a review of the register 90 days before, a decision on the edition to cite 60 days before, and a re-read of every procedure that names the standard 30 days before. If the date moves, the plan moves with it.

EVERY DATE

The stage table, with status

StageWhat it meansDateStatus
10.99New project approved2025-02-26Recorded on the ISO page
30.00Committee draft (CD) registered2025-02-26Recorded on the ISO page
30.20CD consultation initiated2026-01-30Recorded on the ISO page
30.60Close of comment period2026-03-28Recorded on the ISO page
30.99CD approved for registration as DIS2026-07-31Recorded on the ISO page
40.00DIS registered2026-08-05Recorded on the ISO page
40.20DIS ballot initiated: 12 weeks2026-10-05Recorded on the ISO page; current stage
40.60Close of votingnot recordedNot recorded; a 12 week ballot from 5 October 2026 would close on 28 December 2026
50.00Final text received or FDIS registered for formal approvalnot recordedNot recorded
60.00International Standard under publicationnot recordedNot recorded
60.60International Standard publishednot recordedNot recorded; the planning date is an estimate